First Rate has installed sanitary sewer up to the Fourth Street and Oak Drive intersection. All active sanitary services have also been replaced within Phase 2. The contractor is currently installing and testing the new 6” water main between Sherman Avenue and Oak Drive. In addition, Splitrock Landscaping has placed seed, fertilizer, and hydromulch on the disturbed areas within Phase 1.
Next, First Rate will finish installing the water main between Sherman Avenue and Oak Drive. Once the pressure and bacteria testing are complete, they will begin connecting residents to the new 6” water main. The storm sewer, reinforced concrete pipe (RCP), has also been delivered and staged at the east end of the jobsite. This pipe will be installed following the water service installation.


Left: Sanitary sewer main installation. Right: inside a vac truck pothole. Photo includes: the vac hose, pressure washer and located gas service. //Photos courtesy Sayre Associates