Curb & Gutter + Sidewalks installed. Wiring for street lights beginning!

Date:

street project

Curb and gutter has been installed. All last week, crews worked to shape the new sidewalks on North Main Ave. Hooray! As of Tuesday morning, Muth Electric had crews inserting wiring into new street lights.

From the Sayer Associates bulletin: First Rate Excavate’s concrete subcontractor has in- stalled curb and gutter along Main Avenue and 4th Street. Sidewalk has been installed along portions of Main Avenue from 3rd Street to 5th Street. Four fillet sections have been poured at the 4th Street and Main Avenue intersection as well.

First Rate has finished setting up temporary watermain along Essex Street and Granite Avenue. Sanitary sewer has been installed along Essex Street and portions of Granite Avenue. Sanitary sewer services have also been started. Next, First Rate Excavate will continue installing sanitary sewer along Granite Avenue and finish installing the services. The concrete subcontractor will finish pouring sidewalk along Main Avenue and 4th Street. First Rate will then fine tune the aggregate base course in preparation of asphalt surfacing.

Share post:

spot_img

Related articles

Update on Garretson Street project from Sayre Associates, Inc.

The project consists of reconstruction of the street and utilities on Third Street from Depot Avenue to Oak...

Street Project Continues as City Takes Legal Actions

Discernible progress has been made this past week on the much delayed, and much talked about street project...

Log In

Latest articles

Blue Dragon Academy celebrates retirement of Donna Larson

Donna Larson has graced Blue Dragon Academy with her presence for an impressive 8 years. She began her...

Garretson and Sherman city clean-up this week

This coming week, both Garretson and Sherman will be cleaning up. From May 2 until May 6, Sherman residents...

County Burn Ban lifted as of April 28th

On Monday, Minnehaha County Emergency Management lifted the newest burn ban, which was put into place on April...

Expect detours and delays on I-90 exit

The I-90/Brandon interchange project is ready to take its next step in Phase 2, which will cause more...

The Garretson Gazette wins two more peer awards at the SD NewsMedia Association Annual Better Newspapers Contest

For the last several years in a row, the Garretson Gazette has won or placed in the top...

Conversations with Eddie, Part 4

If you’ll recall our last conversation with Eddie Edmundson, we talked about fast cars and his time as...
s2Member®